PROCESS DESCRIPTION AND SCHEDULE
- Receive Proposed
Changes:
The SRC will
receive requests for changes submitted by public participants, categorize
suggested changes and prepare the proposals for reviewing (information will be
accessible through electronic media). (Please see public notification for
proposal format).
Proposals may be submitted beginning July 1st through Sept 15th, 2009.
- Screen Proposed Changes/Formulate
Agenda:
The SRC will
review input received and prioritize issues according to PWE’s mission; develop
a short list of issues to be considered in a formal discussion; publish an
agenda for public review and input. This process will occur from September 16th to
November 15th, 2009.
- Convene/Conduct
Discussions:
The SRC will
provide the opportunity for stakeholders of interest to address and provide
input on proposals. This process will occur from
November 16th to January 15th, 2010.
- Evaluate Proposal/ Develop
Recommendations:
The SRC will
consider all input and post a draft of revisions for comment.
This process will occur from January 16th to March
15th, 2010.
- Receive Comments:
The SRC will receive and
review all comments.
Comments may be submitted from March 16th through
April 15th, 2010.
- Finalize Revisions:
The SRC will process the
information for final approval and publish the final update. Final revisions will be processed
for final approval and published beginning April 16th through June 15th,
2010. |